
Education Centre site dedicated

Education Centre foundations started to be dug

Construction begins

Steel reinforcement for the foundations added

Foundations in place

Ground floor concrete slab almost completed

Ground floor concrete slab completed

Walls being built

Walls progressing well


Ring beam under construction

Ring beam completed

Scaffolding being put in place in order for the first floor to be constructed

Shuttering being put in place so the first floor slab can be cast

Steel reinforcing being put into place just before casting

First floor concrete slab - casting completed

Walls to the upper floor being built
Walls to the upper floor completed

Gable ends and roofing timbers added

Roof tiles now on

External plastering completed

Front view of the building, landscaping done and roadway constructed (see below)

Roadway constructed

Approach road completed

Front of the building

Verandahs completed
|